Hold the nose down until the speed reaches 61 kt, then rotate.
What happened: You started the rotation at 48 kt, 13 kt before the 61 kt rotation speed.
Watch for: Airspeed indicator: 61 kt at rotation
See Departure Roll
Arrival
Make small rudder corrections against a point at the far end of the runway to track the centreline.
What happened: The aircraft drifted off the centreline during the landing roll.
Watch for: Heading indicator: wings aligned with the runway centreline
See Arrival Landing
Preparing for a stable approach will give you time to decide on whether to attempt the landing or going around. Too much altitude with a high sink rate will result in carrying too much speed onto the runway. Configuring flaps and the gear late also won't help the speed decay.
Read more in The Stabilised ApproachStart to finish · 15 stages, 14 in the score
Events
Events
Events
Events
Events
The threshold, the flare and the hold-off. The approach that led to it is the stabilisation gates below.
One stabilised approach gate for a circuit: seven checks where the approach path is 300 ft above the runway. The 1,000 ft gate is an instrument-approach check and does not apply. These checks are the approach's score.
At the 300 ft gate: sink rate 1,286 fpm, more than the glideslope needed, glideslope 6.8° against the runway's 2.8° and centreline 1.1° off, against a 1° limit.
The approach, gate by gate
Side view — the last 1,524 m of the approach.
Plan view — the first 1,524 m of the 2,614 m runway, to the same scale as the side view.
The 347 m touchdown sits inside the full-score zone. The arrival was smooth.
The rest of the report
The Cessna 152 departed runway 11 at MDST Cibao International Airport, executing a departure roll of 590 m which represented 23 % of the available runway. Liftoff was achieved at 49 kt under calm conditions with a temperature of 15 °C, wind 1 kt from 270°, no cross-wind and a 1 kt tail-wind component.
The aircraft entered a left-hand pattern from runway 11, covering less than 1 nm in 59 seconds.
A left-hand pattern crosswind leg followed, also less than 1 nm and completed in 22 seconds.
During the pattern downwind turn the aircraft described a 1 nm arc with an angle to the runway of 48.5°.
The downwind leg extended 3 nm and was flown in 147 seconds.
The base turn was a 1 nm maneuver with an angle to the runway of 34.9°.
The base leg was less than 1 nm and lasted 25 seconds.
A final turn of less than 1 nm was completed in 22 seconds.
On final approach to runway 11 from the west the aircraft maintained a heading of 99.0° at 0 nm and 447 ft AGL.
Landing was made on runway 11, whose length is 2,614 m; the threshold speed was slightly below the target at 51 kt. Touchdown occurred 345 m down the runway at 29 kt with a smooth descent rate of minus 104 fpm, and the touchdown point was offset 6.2 m from the centreline. The total landing distance measured 496 m, representing 19 % of the runway.
Runway rollout alignment was reported as very good.
In total the flight covered 7 nm, required 7 units of time as recorded, and consumed 1 kg of fuel.
The Cessna 152 entered the final approach to runway 11 at MDST Cibao International Airport from the west on a heading of 99.0° at 0 nm and 447 ft agl. Local weather was 15 °C with a wind of 1 kt from 270°, a crosswind component of 0 kt and a tailwind component of 1 kt.
At threshold the aircraft maintained a good height and the threshold speed was recorded at 51 kt, a little below the target value.
Touchdown occurred 345 m down the runway at a speed of 29 kt and a smooth vertical rate of minus 104 fpm. The touchdown point was slightly off centreline by 6.2 m, and the total landing distance measured 496 m, representing 19 % of the 2,614 m runway length.
Runway rollout alignment was very good throughout the deceleration phase.
Maintain the target threshold speed and refine centre-line alignment at touchdown to further improve performance.